A critical machine breaks down. Production stops, and every hour costs money. JD Edwards can help you prevent that, with preventive maintenance. Let's see how.

What JDE maintenance manages

JD Edwards manages maintenance in four parts.

  • Equipment master. The equipment master, P1701, holds every machine, vehicle and asset, with its location and history.
  • PM schedules. Preventive maintenance schedules, based on time, or on meter readings like hours or kilometres.
  • Work orders. Maintenance work orders, to plan, assign and complete the work.
  • Costs. Costs, so you know exactly what each asset costs to keep running.

Reactive vs preventive

Reactive maintenance means fixing things when they break: unplanned downtime, rush parts, and overtime. Preventive maintenance services equipment before it fails, at a planned time, with parts ready in advance.

Reactive

  • Fix it when it breaks
  • Unplanned downtime
  • Rush parts, overtime

Preventive

  • Service before it breaks
  • Planned downtime
  • Parts ready in advance

The preventive maintenance cycle

Here's the cycle in JD Edwards.

  1. Define schedule. You define a schedule for each asset, for example every 500 hours.
  2. PM falls due. When the time or meter reading is reached, the maintenance falls due.
  3. Create work order. A work order is created, with the parts and tasks needed.
  4. Do the work. The technician does the work, and records parts and hours.
  5. Complete & reset. Completing the work order resets the schedule for next time.
  6. Cost to asset. The costs are charged to the asset.

4 maintenance KPIs to watch

Finally, four KPIs to watch.

  • Planned vs unplanned work. The share of planned versus unplanned work. Aim for mostly planned.
  • Mean time between failures. Mean time between failures, which should rise over time.
  • Maintenance cost per asset. Maintenance cost per asset, to spot the machines worth replacing.
  • PM compliance. Preventive maintenance compliance, the share of jobs done on time.

Need a hand with this in your JD Edwards system?

Grace ITCS consultants set this up and support it every day. Talk to a senior consultant, or send us your question.